Bhubaneswar: Deputy Chief Minister K V Singh Deo asked the Power Distribution Companies to expediate restoration of Power Infrastructure in Dana affected areas.
The cyclone DANA has affected the Electrical Infrastructure of the Districts of Bhadrak, Balasore, Mayurbhanj, Jajpur, Kendrapada, Jagatsinghpur.
DISCOMs have deployed the required manpower and material as per the instruction from Government and started restoration soon after the devastation.
Till 2pm, around ten lakh consumers restoration is in progress. More than 90% restoration is expected to be completed by today night.
Out of 106 numbers of affected 33kv feeders, 72 no have been restored. Out of affected 201 Primary Sub-stations, 116 have been restored. Out of 909 no of affected 11kv feeder, 504 no have been restored.
Out of 80135 Distribution Transformers, 39903 no of Distribution Transformers have been restored.
More than 11.4 lakhs of consumers have restored with power supply. All the works are done in a war footing basis, said a senior official.